Our work
Showing 1–24 of 131, newest first

May 2026
Nursery fit-out, first and second fix plumbing
Full first and second fix plumbing for the fit-out of a new nursery, including two 250 litre unvented cylinders, twelve toilets, twelve basins, sixteen sinks and around a mile of copper pipework. The project took six weeks, from an empty warehouse to an operating nursery.

September 2022
Vaillant boiler and cylinder plant room installation
We installed this compact plant room as part of a full house refurbishment, centred on a Vaillant boiler with a low loss header, system pump and zone valves. It works alongside a Joule hot water cylinder and a booster set, with the wiring completed by an electrical contractor.

September 2022
Plumbing, heating and gas for a full house refurbishment
We completed all of the plumbing, heating and gas work on this full house refurbishment. The job took in a new Vaillant boiler and a full heating system, an upstairs bathroom and downstairs shower room, and all of the kitchen and utility plumbing.